Copper was discovered at Kadina in 1860 and water supply was a problem immediately; groundwater in the Copper Triangle (Wallaroo, Moonta, Kadina) is very salty and the area was not suited for building dams. Water was eventually piped from Beetaloo Dam near Crystal Brook.
Water supply for Pt Pirie and Pt Augusta was very limited, and
when Whyalla was developed a pipeline to the Iron Triangle (which
includes these three cities) had to be built from the Murray River
at Morgan. Much of the construction was based at Crystal Brook.
The dam is 32.8 m high, has a crest length of 140 m (not including
the spillway) and has a capacity of 3200 ML (megalitres; 1 ML =
1000 KL). Its catchment area is
48 km2. It is a curved concrete
gravity dam consisting of 43 400 m2
of concrete.
At the time of construction it was the largest concrete dam in
the southern hemisphere.
The dam is on the Crystal Brook, about 15 km upstream from
Crystal Brook township.
Click on the photos with a bright outline to see a
larger copy
Some of what follows was extracted from an E&WS report, Beetaloo Dam:
Historical Account of Construction and Operation; Library Ref. No.
81/32.
Beetaloo Dam was constructed from 1888 to 1890.
The first reference to the Beetaloo works appeared in early 1885 in an article written for the South Australian Register. This article must have created a great deal of interest, because after publication a deputation was sent to the Commissioner for Public Works, to lobby for a water supply to Yorke Peninsula. The Commissioner in turn instructed the Hydraulic Engineer (Mr. Mestayer) to conduct a survey of the Beetaloo Springs area and then to prepare a report.The survey was commenced in May 1885 and the report (parliamentry Paper No. 100-1885) was tabled in September. The report was not optimistic, for although the geology of the area was suitable, (Government Geologists Report P.P. 100-1885) it appeared from the small number of gaugings taken that the flow in the creek would not be sufficient to fill a reservoir of more than 350 ML. However the report did say, that if a further supply could be obtained, then the dam would be quite feasible. This further supply must have been quickly found, because before the end of 1885 the construction of the dam had been approved and the Resident Engineer (Mr. Christopher Jobson) arrived at Laura on the 28th December 1885.
The dam originally envisaged by Mr. Mestayer was to be of masonry construction with a large bywash cut through the right abutment, but after seven quarries had been opened up no suitable stone had been found that could have been quarried cheaply. Even though there was considerable pressure to build a masonry dam (because of high unemployment among masons) it was decided to use concrete. It was a large and ambitious project being the largest concrete dam built in the southern hemisphere. Because the project was such a departure from previous works, both in design and materials, no suitable machinery was available so the machinery and plant were designed and made by the Waterworks.
By the time the Resident Engineer arrived at the site no final drawings had been prepared as the project had been commenced quickly in an effort to help unemployed labourers. This was possible because the initial work of clearing foundations, building catch dams and clearing the reservoir area required only preliminary sketches.
During 1886 work commenced on clearing the foundations and sinking trial shafts, with the main effort being concentrated on clearing the reservoir area and building silt trap dams. These small dry rubble masonry dams were built with the base of the dam 1.6 metres above full supply level of the reservoir and were on the twenty main creeks emptying into the basin. Two earthern catch dams were built, one in Walters Gully and one on Crystal Brook. These were connected with a water race. Catch drains were cut 3 metres above full supply level and these discharged into the catch dams. These catch drains and dams were constructed in an effort to protect the works from flooding and also to provide the water needed for the construction of the main dam. The overflow from the Walters Gully dam was diverted past the main dam excavation by means of a race, which effectively kept the dam foundations dry.
Water was scarce during 1886 and soon after their completion the catch dams were used to supply Bute via 80 kilometres of temporary main. The only interruption to this supply occurred in November 1886 when a heavy storm brought 65 mm of rain in 2 hours accompanied by hailstones about the size of tomatoes. After about 20 minutes the creek came down and for a while the catch dams held. However, when the hail melted the flow increased dramatically and the catch dam on the main creek was washed away. During this flood a man named Wilson attempted to cross the creek from one camp to another using only a rope and was washed away and drowned. His body was recovered about 1 1/2 hours later having been washed 5 kilometres downstream.
During 1887 most of the preparations for the mixing and placing of the concrete were completed with all the machinery in place and tested. Stone was broken and stockpiled, tramlines laid and wood stacked to be used later to fuel the steam powered machinery. The casks of cement were brought from Port Pirie and stored in the sheds so that by the end of 1887 all was in readiness for the pouring of the concrete which began on February 28th 1888. Concrete was poured continuously until May 1889 when the non-arrival of cement stopped pouring until the end of July 1889. The work then proceeded satisfactorily until October 1890 when the dam was finally completed.
When the dam was built it was expected to collect sufficient runoff to fill the reservoir once annually (3600 ML). This later proved to be over optimistic as there was only sufficient water to fill it each year. An all year round supply of spring water supplements the runoff from the catchment. The main sources being in Norman's Gully where a shaft and cross-cut were excavated in 1930 and Mary Springs where a tunnel was excavated in 1899 to intercept the springwater. In 1936 a graded earthenware pipe was constructed along the creek bank to carry the spring water from Mary Springs to the reservoir. During a major flood in 1975 a section of the pipe was washed away and remains in disrepair.
To stop water seeping beneath the wall of a dam it is necessary to
remove any permeable earth or weathered rock. On the first attempt
to do this beneath the proposed Bundaleer dam there was a disastrous
collapse which caused the death of five men and the injury of two
more.
This photo, taken in 1900, shows how the trench was propped to stabilize it. Placing such large logs must have been demanding considering the lack of machinery at the time.
This trench was later filled with clay to produce a watertight barrier beneath the dam wall.
The Honorable (I think the term meant something in those days) Tom
Playford, Premier of S.A. opening the valve to allow water from
Baroota Reservoir to flow into the BHP Reservoir at Whyalla,
31st March 1943.
Home